The uncertainty over the construction of a protective duct for a 110 kV underground power cable, which had stalled work on the Elathur-Pavangad railway overbridge in Kozhikode, has been resolved. The decision was taken at a meeting attended by Public Works Minister P.K. Basheer and senior officials in Thiruvananthapuram recently, where the Minister directed the Roads and Bridges Development Corporation of Kerala (RBDCK) to bear the cost of building the protection duct.

Construction of the Pavangad flyover officially began on March 10, 2026, but foundation work had been pending because the underground transmission cable runs directly along the proposed alignment. The Kerala State Electricity Board (KSEB) initially submitted an estimate of about ₹5.50 crore to relocate the cable. To save costs and avoid further delays, it was decided to modify the pile layout so that the existing cable would not need to be shifted.

With KSEB's approval, the estimated cost was brought down to approximately ₹1.10 crore after the RBDCK reviewed the alignment and decided to reduce the duct's length by nearly 60 metres. The meeting in the capital was convened at the request of M.K. Raghavan, MP, who noted that delays in the flyover project were causing severe commuting hardships for the public and driving up overall project costs.