The Kerala State Electricity Board (KSEB) has told the Kerala State Electricity Regulatory Commission (KSERC) that its power purchase agreement with VEH Global India Pvt Ltd was an "exceptional and limited-period contingency measure and not as a regular arrangement." The commission, headed by T.K. Jose, has admitted the KSEB petition along with replies to 17 queries and will hear the matter on December 16.

The agreement, which had kicked up a political storm in Keralam, covered the purchase of 200 MW for six hours every evening from September 23 to October 31, 2026. The Opposition Left Democratic Front (LDF) had alleged that the deal would cause a heavy financial loss to the State, as wind power cost below ₹4 per unit.

According to the KSEB, the maximum energy charge for the 39 days would have come to 46.80 million units, with an energy charge of ₹51.48 crore. The excess charge on account of purchasing above the ceiling limit would be ₹4.68 crore, it said. On purchasing power at ₹11 per unit against the commission-set ceiling of ₹10, the KSEB observed that the circumstances necessitating procurement, the availability of alternative sources, the urgency of supply, the period and time blocks of procurement and the consequences of non-availability of power are equally relevant considerations in an emergency.

Documents show that the KSEB decided to forgo renewable purchase obligation (RPO) benefits for the purchase. Replying to the commission's query on the reasons, the KSEB said the agreement describes the supply as "wind-based brown power" without environmental attributes and that it has sought no RPO credit for the purchase. RPO, under Section 86(1)(e) of the Electricity Act, 2003, requires entities such as distribution companies to source a certain percentage of their total electricity consumption from renewable energy sources.