The 443-metre Jakkur Railway Overbridge in north Bengaluru, expected to ease traffic between Jakkur and Yelahanka, has been completed after a 15-year wait and will be inaugurated on Wednesday. Chief Minister D.K. Shivakumar will inaugurate the overbridge along with the Geddalahalli railway vent, and will also lay the foundation stone for a rotary flyover at the IOC Junction on Maruthi Sevanagar Main Road and the extension of the Baiyappanahalli railway overbridge. The projects fall under the Bengaluru North and East City Corporations.

The overbridge connects Jakkur village to roads leading to Yelahanka via Raithara Santhe, offering an alternative route linking areas around Amruthahalli, Kempapura and Thanisandra to localities around Yelahanka. According to the Greater Bengaluru Authority, motorists from around Jakkur currently cover an additional distance of over 5 km to avoid the railway crossing, and the bridge could save commuters approximately 15 minutes while reducing the traffic burden on Ballari Road. Urban mobility expert Sanjeev Dyamannavar said the road could particularly benefit employees commuting to Manyata Tech Park from Yelahanka, as hundreds of vehicles can use the Railway Parallel Road and avoid three traffic signals.

The project, initiated by the South Western Railway in 2011, faced several delays, primarily over land acquisition. The erstwhile Bruhat Bengaluru Mahanagara Palike began acquisition in 2017, but only 33 of the 48 properties required were acquired at a cost of ₹25 crore. In 2018, railway authorities completed five girder spans, but work on the reinforced concrete retaining wall remained incomplete. The BBMP revived the project in March 2024 with a fresh work order and a 10-month deadline, but remaining land acquisition delayed the work again. Six additional properties were subsequently acquired with compensation of ₹18.5 crore paid, and ₹15 crore was sanctioned for the remaining construction.

The four-lane overbridge, with a carriageway width of 7.5 metres, has been constructed using composite steel girder technology, with a 40.46-metre-long steel girder and a Reinforced Earth wall.