The four-lane elevated corridor proposed along East Coast Road from Thiruvanmiyur to Uthandi in Chennai faces further uncertainty, with State Highways Minister Aadhav Arjuna hinting the project may be cancelled even though a tender has been finalised and work allotted. Speaking to presspersons on November 13, the Minister said the project had been referred to a high-level committee and would be cancelled since the tender was awarded before land acquisition was completed, adding that work awarded without completed land acquisition would be a non-starter.

Official sources, however, said the construction firm had represented to the Tamil Nadu Highways State Authority on October 12 that land acquisition for the right of way was already 90% complete, sufficient to begin work, and that land needed for ramps would not affect commencement. The 13.4-km project is being executed under the hybrid annuity mode, with the State contributing 40% of the cost and the contractor bearing the rest. It is intended to ease congestion on a stretch that has 17 traffic signals across roughly 14 km and 347 crossroads between Thiruvanmiyur and Uthandi, and was designed to address bottlenecks at key junctions including Lattice Bridge Road, Akkarai and Injambakkam.

The estimated cost in the first tender followed the 2024 Schedule of Rates; a fresh tender would reportedly cost at least 20% more due to inflation over the last two years. A retired Highways engineer said the contractor could seek a court stay on a proposed fresh tender until dues are settled, potentially delaying the project further, citing the Chennai Port–Maduravoyal Elevated Corridor as an example of delays when a contract is paused. The former official said letting the present contractor proceed under the new design would be easier, and that allowing projects to start once 90% of acquisition is complete has been past practice.

The report also noted that after the Tamilaga Vettri Kazhagam came to power, the Highways Department cancelled tenders for the Oragadam–Cheyyar Industrial Corridor Road Project, a four-lane, 43.4-km stretch connecting Valayankaranai and Manampathy, though there is no clarity on the reasons or on when fresh tenders would be floated. Tenders for a section of the Chennai Peripheral Ring Road from Singaperumal Koil to Poonjeri near Mamallapuram were also cancelled, citing administrative reasons.