Chennai Metro Rail Limited has completed the launching of all U-girders on the Koyambedu-Alandur stretch of its phase II project, according to a press release. The corridor, which runs 14.5 km under the 118.9-km phase II project, is slated to open next year, and track work on the stretch is also in advanced stages.

U-girders are precast concrete structural beams used in the construction of elevated viaducts, over which trains run. The final girder on the stretch was launched on Sunday between Butt Road and Kathipara Junction over Paul Wells Road, using two high-capacity hydraulic cranes.

The completed stretch comprises 911 U-girders ranging in length from 15 metres to 33.33 metres, with an average weight of approximately 135 tonnes. The release said erecting works were carried out using multiple methodologies, including launching girders and high-capacity hydraulic cranes, depending on site conditions and the requirements of each location.

The release said the work faced several challenges, including space constraints and underground and overhead utility lines at locations such as Kaliamman Koil Street, Butt Road and Paul Wells Road. The integrated flyover along Mount-Poonamallee Road added to the complexity, it said. The last girder at Paul Wells Road was particularly challenging owing to a space crunch, with one crane positioned within nearby church premises and the other in a narrow street, the release said. For another girder at the same location, the Metro Rail mobilised an additional 1,000-tonne-capacity crane to complete the work within a tight time frame and in very limited space.