The Greater Chennai Corporation (GCC) has eased conditions for its 2026-27 road relaying contracts, according to a corporation official. The changes are aimed at widening contractor participation and curbing cartelisation of bidders.

Work orders for the contracts will be generated through the Tamil Nadu government's e-procurement portal, hosted by the Union government's National Informatics Centre. Under the new procedure, orders will be issued online once financial bids are opened, negotiations are completed and letters of acceptance are issued, so contractors will no longer need to approach officials separately for the document required to begin execution.

The GCC has also revised the rules on additional security deposits. Only the lowest bidder must now furnish the deposit, within two days of the first negotiation, through NEFT, RTGS or an electronic bank guarantee; previously the requirement applied at the tender-opening stage. The change is intended to protect the confidentiality of financial bids, the official said. Bidders may use owned or registered leased centralised hot mix plants with a valid consent to operate certificate from the Tamil Nadu Pollution Control Board, located within 40 km of the GCC boundary, and may participate in more than one package if they meet eligibility conditions.

The proposed works cover 753 roads across all 15 zones, including 66 bus route roads, over a total length of 167.55 km, of which 43.86 km comprises bus route roads. The estimated cost is ₹149.12 crore, including ₹68.31 crore for bus route road works. Tenders have been scheduled for November 27, December 3 and 7, 2026, according to project details.

The GCC will retain 2.5% of the contract amount during the three-year defect liability period as a safeguard against defects, the official said; contractors remain responsible for rectifying defects during this period and can replace the withheld amount with an e-bank guarantee after completing the work. The official said GCC tenders had generally attracted bids above the estimated cost in the past, but the corporation had recently been receiving bids quoting discounts of as much as 20% to 30% below estimates. The GCC rejected a request to relax the pollution consent requirement, citing National Green Tribunal directions, but permitted registered leased plants subject to the prescribed conditions.